Construction of New Pak Secretariat Block Islamabad

Pak PWD is engaged in the construction of New Pak Secretariat Block at Islamabad. The construction of new blocks of Pak Secretariat, costing Rs3.47 billion, started in 2008.The project was to be completed in 2010 but due to paucity of funds, it witnessed delays. So far over Rs2.00 billion has been spent on it. Initially combined tenders of electrical and civil works were invited from the pre-qualified contractors with Elektra System coming up with the lowest bid of Rs378 million. However, these tenders were rejected and the work was split up. The total covered area of the project is 769200 Sft with total cost of the project is Rs. 3476.362 (M). The project consists of Eleven (11) storey building structure with all state of the art facilities.  Presently about 100% of the work on the project has been successfully completed.